Combined Sewer Overflow (CSO)
Project
2. How does the CSO retention/treatment shaft work?
3. Were other approaches considered?
4. Why is a treatment shaft being constructed in our
neighborhood?
6. How long will construction take?
7. Will restoration of the site happen only after
construction is completed?
8. What is the plan for site restoration?
9. How will we know if construction is going according
to schedule?
10. Why was permit parking implemented in all of Riverbend?
11. What are the permitted hours for construction?
12. Who do I contact if noise violations are taking
place at the site?
14. What dust control procedures will be implemented?
15. What if construction activity causes damage to my
house or property?
16. Where can I get more information on this project?
It is a project to meet the
requirements of the Federal Clean Water Act of 1972 pertaining to correcting
water quality problems caused by discharges from combined sanitary/storm water
sewers. The United States Environmental Protection Agency has cited combined
sanitary/storm water sewer overflow (CSO) discharges as a significant source of
pollution to the nation’s surface waters.
In our nation’s history,
combined sanitary/storm water sewer systems were built in the mid to late 1800s
and early 1900s at a time when wastewater treatment plants did not exist.
Nearly all the combined sanitary/storm water sewer systems built in this era are
still in use. At that time construction of combined sanitary/storm sewer
systems was encouraged to help eliminate emerging widespread safety and health
concerns in our growing urban centers. Construction of this type of sewer was
abandoned in the 1940s-50s with the advent of construction of wastewater
treatment plants built to handle separated sanitary sewerage. Approximately
sixty six percent of
The Federal Clean Water Act
of 1972 now requires the overflows from combined sewers to be eliminated or
treated to meet federal water quality discharge standards for body contact and for
supporting healthy aquatic life.
1. Separating combined sanitary/storm sewer where
practicable and
2. Where separation is not practicable construct
retention/treatment facilities that store and treat discharges
to meet federal water quality standards for body contact and for supporting
healthy aquatic life when discharges occur.
2. How does the CSO retention/treatment shaft work?
The treatment shaft system is designed to reduce overflows from the existing 45-55 to 2-3 per year and
provide treatment of those discharges to meet federal water quality standards
for body contact and for supporting healthy aquatic life.
3. Were other approaches considered?
Yes. The City spent several
years and thousands of hours working with federal and state officials and City
residents reviewing numerous alternatives for addressing the combined sewer
overflow problem, including sewer separation.
The City selected partial sewer separation and the treatment shaft
approach where separation was not practicable or economical. The treatment
shaft design was selected because it met the federal CSO control requirements,
provided the greatest environmental benefit with the least disruption to
neighborhoods and businesses and was the best in terms of construction cost and
long term operation. When the CSO Project is completed it will be the largest
public works project in
4. Why is a treatment shaft being constructed in our
neighborhood?
The area along the
Design
of the CSO control system requires that the treatment shafts be located at or
near the existing sewer overflows.
5. I read that some of the similar projects
that are in varying stages of
construction have shifted or cracked, delaying the project. What assurances are there that similar problems
will not affect the shafts still needing to be constructed?
Some CSO projects currently
under construction have encountered problems during the shaft sinking process,
but steps are being taken now to resume work and make the necessary repairs. These
are large and complicated projects and it is not unusual to encounter some
difficulty during construction. Some of the contractors involved with the other
projects are less familiar with the sinking process and it is taking them
longer to complete. The contractors
working near
6. How long will construction take?
The treatment shaft
installation will take 30-36 months to complete the construction and final
restoration of the affected sites.
7. Will restoration of the site happen only after
construction is completed?
No, some restoration can
begin in various areas of the site as soon as work in those areas has been
completed.
For example, final shoreline
restoration along some portions of the
8. What is the plan for site restoration?
Each site is different and
the final restoration plan is developed to meet MDEQ standards, the needs of
the residents of the surrounding area and the City’s environment as a whole.
For CSO project #8, the
draft final restoration plan was developed by JJR, Inc., a landscape architect
firm retained by the City to obtain approval from the MDEQ to construct this
project in a floodplain. The plan provides detailed site
restoration drawings showing floodplain, river, wetland, forested and grassland
features. It also describes plant stock consistent with native species that
will provide habitat, attract songbirds and increase wetland and floodplain
functions.
9. How will we know if construction is going according
to schedule?
Dearborn DPW has prepared a
timeline of the critical path construction activities. The
timeline will be updated quarterly.
Current Schedule and Progress
(as of April 2008):
The site is proceeding as
scheduled.
Updates to the schedule and
construction activities will be posted quarterly.
10. Why was permit parking implemented in all of Riverbend?
Neighbors had voiced concern
about construction workers parking on the residential streets during
construction when more than 80 workers may be on site at a time. City officials and Riverbend
representatives working cooperatively agreed that permit parking throughout the
entire neighborhood was the best solution to prevent construction vehicles from
merely moving from one street to the next.
Those interested in securing parking permits or would like additional
information please call the Dearborn Police Department at 313 943 2275.
11. What are the permitted hours for construction?
City ordinances restrict
construction activities to occur between 7:00 a.m. to 7:00 p.m. Monday through
Saturday. The contractors may also
perform site maintenance operations between 7:00 pm and 10:00 p.m. but cannot
cause elevated noise levels during that time.
12. Who do I contact if noise violations are taking
place at the site?
Complaints can be made to
the Dearborn Police Department by phone at 313 943 2241at any time. In addition, residents can also contact the
Dearborn DPW from 8am to 5pm Monday through Friday at 313 943 2075.
13. I understand that a control building will be
constructed with the treatment shaft. What will the control building look like,
what operations will take place there and what chemicals will be stored there?
An automated control
building will be constructed at the treatment shaft site. The
building is necessary to house the disinfection chemical (liquid chlorine
bleach), and the electrical, plumbing and mechanical equipment needed to
operate the facility.
The control building will be
one story tall and approximately 40’ x 50’. The outside of the building will be
brick, with roofing and trim material selected to fit with the architecture of
the surrounding area. The residents of the area and other concerned individuals
or groups will be invited to comment and review the final exterior design.
The chemical stored there
will be sodium hypo chloride, better known as common household bleach. About 19,000
gallons of this liquid will be stored in two double wall tanks under the
building with leak detection monitors. The bleach will be blended with the CSO
flows to kill harmful bacteria when it is anticipated that an overflow to the
river will occur, which is expected only 2-3 times per year. To keep the bleach
at proper strength and to refill after treatment events, the tank will need to
be replenished 3-4 times per year.
14. What dust control procedures will be implemented?
Temporary and permanent
seeding, soil moisture control, street sweeping using vacuum or pickup-type
equipment will all be used to control dust and soil that may be tracked out
from the site and onto City streets on a daily basis.
15. What if construction activity causes damage to my
house or property?
The City has taken every
precaution to protect against public and private property damage that might
occur due to construction. Seismic ground monitors have been installed along
the perimeter of the property to insure ground vibrations remain below levels
that may cause damage to adjacent structures. Air monitoring equipment and
noise measuring devices are being used at the site. Prior to construction
activity commencing the City required video and neighborhood inspection of all
properties adjacent to the site.
Residents need to document
any damage that they feel has occurred as a result of the construction
activities at the site. Documentation that shows before and after conditions
(i.e. pictures, videos, etc.) is the most valuable means of insuring claims can
be adequately reviewed and resolved. Any damage or approvable loss that may be
caused by construction of this project will be corrected as a project expense.
Please contact Dearborn DPW
regarding any questions or claims pertaining to property damage you feel has resulted because of the construction of this
project.
16. Where can I get more information on this project?
Persons requesting further
information can contact:
James Murray
Deputy Director
313 943 2073